Question

??i just have an assignment in project management class. i need someone who is familiar and expert with project management class. please take a look for the assignment and if you could be able to do it , just notify me. thank you ?


College of Business and Technology, Morehead State University

Exam 3 Hands-On Part
IET 320 Project Management (Spring 2016)

Read the instructions carefully to complete this exam.
Using Microsoft Excel and the data in the tables below, answer the following questions. Assume the
project is planned for a 12-month duration and $270,000 budget.
a. Earned value
b. Schedule performance index and estimated time to completion
c. Cost performance index and estimated cost to completion
Planned Costs

Jan
Staffing
Blueprinting
Prototype Dev.
Full Design
Construction
Transfer

Feb
7

Mar
8
5

Apr
5
3

May

9
4

Jun

9
3

% Comp.
100
100
70
9
50
28
25
12
0

Actual Costs

Jan
Staffing
Blueprinting
Prototype Dev.
Full Design
Construction
Transfer

Feb
9

Mar
9
6

Apr
5
4

May

10
5

Jun

10
4

12
30
14

Microsoft Excel should be used to complete this exam and the answers should be marked in the Excel file. Save
the Excel file as Exam03YourName.xlsx and submit the Excel file to the Blackboard course website by the end of
May 6, 2016.